Adaptive Multifactor Authentication is officially here to make your online experience more secure than ever before. With this update, you can expect:
To learn more about Adaptive MFA, including how it works, please click here.
Before the wind turbines can begin to generate electricity, several stages of construction must be completed. The construction schedule for each stage includes:
Safety is our number one priority during construction. Our team is committed to building the Gratiot Farms Wind Project in the safest manner possible to avoid lost-time incidents and injuries involving the public or our employees. Interested in seeing more?
View map of project boundaries and wind turbine locations.
The anticipated construction schedule for Phase III is as follows:
Laydown Yard: The laydown yard is the “command center” for of the construction project. It is located on Grant Road just north of Cleveland Road (M-57). Be alert for construction traffic around this area.
Support Solar Gardens
Join the solar energy movement and help preserve what we love about Michigan.
About Solar GardensFor the best performance on this website and others, please upgrade your browser. For suggestions to find the best web browser for you click here.