Avoiding Service Connection Challenges

Proper Planning is Key

There’s no getting around it, there are a lot of steps to adding new electric or natural gas service. But you can avoid needless delay, costs and frustration with careful planning. This page outlines some of the most common pitfalls in the service connection process, and how to avoid them.

Research Your Property Rights


Property rights delay installation of new energy service more often than any other factor. Property rights include easements, right of ways and permits.

One of the best ways to help your service installation move forward is for you to contact your neighbors early in the process to obtain required easements. Your Project Coordinator can give you suggestions on how to go about contacting your neighbors. It is well worth your effort, to help avoid potential delays of weeks or months.

If you haven’t purchased property yet, we recommend you investigate needed permits, easements and Right of Way documents before you purchase.

Do You need to Install Conduit?


When to Install Conduit


Installing conduit could help avoid possible installation delays and potentially save you money, especially in the winter months when the cost of trenching increases. To learn more, view our Why You Should Consider Installing Your Own Conduit video on our Service Connection Videos page.

While installing conduit may be a great option in certain situations, it must be discussed with your project coordinator in the Scoping Phase of your project to determine if installing conduit is appropriate for your project. Each system – electric or gas – has different code and construction requirements that are specific to your job, and proper coordination ensures the correct approach is used. To avoid additional costs and delays, never purchase or install conduit prior to receiving a finalized design and the Conduit Criteria Guidelines from your project coordinator.

How to Prepare for Installation


Clear the Site

Be aware of the planned path for underground service and keep it clear (unless conduit is installed). Plan on how our trucks will access your property from the energy mains to your site. Make it easy for our crew to access the building site; keeping those routes clear as well.

Call MISS DIG 811

Our installation team will call MISS DIG 811 to mark your site. However, if you notice missing stakes, damaged stakes or underground lines that haven’t been properly marked, please notify your Project Coordinator, who will call for a re-stake.

Have Your Meter Inspected

You need to have your meter inspected and properly marked with an inspection sticker or we won’t be able to connect to it. Your Project Coordinator can tell you how to get this done.

Properly Calculate Trench/Conduit Depth to Final Grade

Maximum depth allowed is 48” for electric service. If trench depth is 44” but there are 6” of topsoil yet to be delivered, this would put depth to final grade at 50”, which be a code violation.

Mark Your Property for Safe and Timely Installation


All facilities must be marked or staked.

If any staking is destroyed or missing; crews will not be able to conduct work.

Another common issue, materials along a marked, proposed trench. This is more common in lake front neighborhoods or anywhere where smaller lots are common, which is one reason owner installed conduit is encouraged.

Be Sure to Mark These Features

Septic systems
Sprinkler systems
Electric fence systems
  • Invisible and conventional
Drain tiles
Utility lines to pole barns or other out buildings
  • If the out building doesn’t have a meter on it, it is your responsibility to mark all utility lines.




Gas or electric lines to pool heaters
Water lines to pools or pool filters
Utility lines to outdoor kitchens
Power lines for outdoor pumps or wells
Power lines to landscaping features

  • Fountains
  • Lighting
Charging stations
THIS LIST IS NOT ALL INCLUSIVE

Avoiding Issues With Cost Estimates and Payments


Cost Estimate Issues

In many cases we will provide you with an initial cost estimate for installing your natural gas or electric service. This initial estimate is usually based only on the distance from the main gas or electric lines. Your initial estimate does not include permit fees, boring fees, tree trimming, longer routes or the installation a larger service to accommodate larger loads. PLEASE NOTE: These factors can more than triple the initial estimate.

Payment Issues

When you ask us to install new energy service for you, we set up a separate construction account for those cost, a different account than your regular monthly energy bill. Your Project Coordinator will give you instructions on how to make sure your payment goes to your construction account. It is important that you follow those instructions, because if you mistakenly pay your construction fee to your monthly energy account it can delay your installation by weeks.