Saginaw Trail Pipeline Project

Delivering Natural Gas Value

The Saginaw Trail Pipeline is a four-phase, $610 million project that’s part of a larger strategic commitment to the energy future of Michigan.

  • This project will replace vintage pipeline dating back to the 1940s with new pipeline.
  • New pipe will help us move natural gas more quickly, safely and efficiently.
  • It could create as many as 450 jobs each year.
  • Michigan contractors, goods and services will be used whenever practical.

  • We are investing hundreds of millions of dollars to upgrade our natural gas infrastructure to benefit the over 1.8 million homes and businesses we serve throughout Lower Michigan.
  • About 20 crews with different responsibilities will coordinate to remove the old line and install new pipe.
  • Safety is our top priority, and daily briefings are key to a successful project.
  • We restored 93 acres of the first phase construction area using a special seed mix containing native grasses and wildflowers to attract bees, butterflies and other pollinators losing habitat across the country.
  • During the first phase of construction, we discovered turtle eggs in the right-of-way, removed them for safe hatching and released them back into their native habitat.
  • Crews locate underground pipes and wires, remove trees, rocks and debris, and strip the top soil. Fences are installed to help control erosion along wetlands, streams and drain crossings.
  • The old pipeline is removed, cut into sections and removed according to environmental best practices.
  • Pipe is transported to the right-of-way, where it’s laid out, bent to follow the terrain and welded together. Technicians inspect the welds, the pipe is coated to prevent corrosion and re-inspected.
  • Crews dig the ditch. The pipe is lifted and lowered into the ground and tied in to city gates or other junctions.
  • When the pipeline has to cross roads and highways, we bore safely underneath and pull the pipe through according to industry best practices.
  • The pipe is buried and a crew ensures the land is graded and flat.
  • We leave it better than we found it by cleaning up the construction area and planting new grass seed. In some wild areas and wetlands, we may use a special mix to attract pollinators such as bees and butterflies.

Our Plan

In total, we’ll be replacing 78 miles of pipeline with 94.4 miles of newly installed pipeline.

Phase 1 - Completed Clio city gate (CG) to Evon Road valve site 18.5 Miles
Phase 2 Evon Road to Zilwaukee CG 18.5 Miles
Phase 3 Clio CG to Grand Blanc CG 29.2 Miles
Phase 4 Grand Blanc CG to Clawson Control 28.2 Miles
  • Crews of union skilled trades workers from Consumers Energy and Welded Construction plan to remove old pipe along the Saginaw Trail Pipeline route and installing a new, larger pipeline.
  • While the pipeline travels primarily through rural agricultural areas, it will be rerouted around two large urban areas of Saginaw and Flint.
  • In addition to replacing pipe, we’ll also rebuild city gate facilities, which reduce the pressure of natural gas flow to transport it safely through smaller distribution pipelines to farms, homes and businesses.
  • Each construction phase must be complete in time for the upcoming heating season. This requires world-class performance.

Latest News

The first phase of the project was completed in 2017. Construction on the second phase, which reroutes the pipeline away from a more urban area in Saginaw, is slated to start in spring 2018. We're also laying the groundwork for future phases, which includes surveying and securing easements and permits.

saginaw-trail-pipeline-map


Working Together for Safer Communities

Because we are committed to being a good neighbor, we’re communicating clearly with communities in the project area. Whenever practical, the pipeline will follow existing easements.

Our construction teams will follow best practices such as:

  • Burying pipeline at least three feet deep in all areas.
  • Burying pipeline four feet deep in agricultural areas.
  • Locating all drain tiles on impacted farmland and, when necessary, repairing damaged tiles due to our construction.
  • Consumers Energy will provide fair compensation for crop damage to impacted landowners.

Caring for Michigan's Environment

Consumers Energy is working carefully to protect the environment and local wildlife.

We’ve completed a detailed environmental inventory of the project area – including all wetlands, drains and stream crossings – and will work with applicable federal, state and local agencies to consider all environmental concerns.

These efforts include identifying and protecting any threatened or endangered species such as bats and their habitats. An environmental inspector will be on-site daily during construction, and a herpetologist will help reptiles such as snakes and turtles that may be impacted.

Saginaw Trail Pipeyard

Our 80-acre campus in Thetford Township near Flint will serve as home base for the project for the next five years. The site has a field office, ample room for materials and equipment, and easy crew access to the entire project area. We’re happy to be part of the local community and look forward to a positive working relationship.

Learn More

Public: 989-723-9755

Media: 586-918-0597